Performance Evaluation Study of Cost and Time Benchmarks on Construction Projects Using the Earned Value Management Method: Road Duplication Paving Project in Zliten, Libya- Case study

Authors

  • Mustafa M. Sofia Department of Mechanical and Industrial Engineering, Faculty of Engineering, Alasmarya Islamic University, Zliten, Libya
  • Mustafa O. Hakoumah Department of Mechanical and Industrial Engineering, Faculty of Engineering, Alasmarya Islamic University, Zliten, Libya
  • Atiya N. Njea Department of Civil Engineering, Faculty of Engineering, Alasmarya Islamic University, Zliten, Libya

DOI:

https://doi.org/10.59743/jmset.v11i2.199

Keywords:

Earned Value Management EVM, Construction Projects, Cost Control, Cost and Schedule Performance Indicators, Schedule Control

Abstract

One of the most significant challenges facing engineering project management, including research and development, construction, and other projects, is completing projects according to schedules and budgets. These challenges often stem from shortcomings in the application of technical, time-related, and financial planning and monitoring mechanisms. Earned Value Management (EVM) is a powerful and effective tool for addressing these shortcomings by linking actual progress of completed work to time taken and cost incurred, and comparing it to the project's planned baseline. This paper aims to highlight the vital importance of adopting the EVM methodology in monitoring the implementation of construction projects and its use as a benchmark for evaluating cost and time performance. The paper provides a comprehensive overview of key EVM concepts and indicators, including Values of Planned, Earned, and Actual, Cost Variance, Schedule Variance, as well as Performance Indicators (CPI, SPI) which reached 0.76 and 0.90 respectively, and forecasting indicator (EAC) which is 6.44 M Libyan dinar, the project appears to have experienced a financial overrun of approximately 31.8% and a schedule delay of approximately 10% from what was originally planned. The paper also analyzes the implications of these indicators in different project performance scenarios, emphasizing the role of EVM in identifying deviations early, and guiding decisions for corrections that lead to the successful completion of projects. The contribution of this study the significance of this work is in importing sensitivity testing as a rare case study within the frameworks of infrastructure projects in Libya.

Downloads

Download data is not yet available.

References

Abdelrahman, S. A., & Nassar, A. H. (2024). Integrating theory and practice in value engineering within Egypt’s construction industry. Journal of Engineering and Applied Science, 71(1), 188.

Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12-23.

Aramali, V., Gibson Jr, G. E., El Asmar, M., & Sanboskani, H. (2023). Novel earned value management system maturity framework and its relation to project performance. Journal of Construction Engineering and Management, 149(6), 04023031.

Budd, C. I., & Budd, C. S. (2009). A practical guide to earned value project management. Berrett-Koehler Publishers.

Christensen, D. S. (1996). Project advocacy and the estimate at completion problem. The Journal of Cost Analysis, 13(1), 35-60.

Czarnigowska, A. (2008). Earned value method as a tool for project control. Budownictwo i Architektura, 3(2), 15-32.

Doloi, H. (2013). Cost overruns and failure in project management: Understanding the roles of key stakeholders in construction projects. Journal of Construction Engineering and Management, 139(3), 267-279.

Dvir, D., Raz, T., & Shenhar, A. J. (2003). An empirical analysis of the relationship between project planning and project success. International Journal of Project Management, 21(2), 89-95.

Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management. Project Management Institute.

Kerzner, H. (2025). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Lipke, W. (2003). Schedule is different. The measurable news, 31(4), 31-34.

PMBOK Guide (2017). A Guide to the Project Management Body of Knowledge, 6th ed. Project Management Institute.

Projects Implementation Authority. (2024). Technical and financial report of Contract No. 200/2024. Ministry of Transportation, Government of National Unity of Libya.

Rad, P. F., & Levin, G. (2002). The Advanced Project Management Office: A comprehensive look at function and implementation. CRC press.

Vargas, R. V. (2003). Earned value analysis in the control of projects: Success or failure. AACE International Transactions, 21(4), 211-214.

Downloads

Published

2025-12-31

Issue

Section

Articles

How to Cite

Sofia, M. M., Hakoumah, M. O., & Njea, A. N. (2025). Performance Evaluation Study of Cost and Time Benchmarks on Construction Projects Using the Earned Value Management Method: Road Duplication Paving Project in Zliten, Libya- Case study. Journal of Marine Sciences and Environmental Technologies, 11(2), E 33-46. https://doi.org/10.59743/jmset.v11i2.199